Construction5 min read985 words

The Contractor’s Guide to Concrete Sizing & Ready-Mix Orders

How to calculate cubic yards without running short, understand batch plant short-load fees, and choose between bags and ready-mix trucks.

Key Principle:Always add a 10% waste buffer to account for subgrade grade variations and prevent structural cold joints.

The One Formula: Cubic Yards

Every concrete order starts with the same formula: cubic yards = length × width × thickness, with all dimensions in feet, divided by 27. One cubic yard is 27 cubic feet (3 ft × 3 ft × 3 ft), and it is the unit ready-mix suppliers sell by. Thickness is usually given in inches, so divide it by 12 first: a 4-inch slab is 1/3 of a foot thick. A 20 × 15 ft patio at 4 inches is therefore 20 × 15 × (4 ÷ 12) = 100 cubic feet, and 100 ÷ 27 = 3.70 cubic yards. The same formula works for walls — length × height × thickness — and for round piers, where the volume is π × radius² × depth. If you already know the area in square feet, a shortcut helps: one cubic yard covers 81 sq ft at 4 inches thick, 65 sq ft at 5 inches and 54 sq ft at 6 inches. So a 450 sq ft driveway at 4 inches needs about 5.56 cubic yards by the shortcut — use the exact formula for the order and the shortcut only for a quick check.

Worked Example: A 20 × 15 Ft Patio

Take a 20 ft by 15 ft patio slab, 4 inches thick. Net volume is 20 × 15 × (4 ÷ 12) = 100 cubic feet, or 3.70 cubic yards. Add the standard 10% waste buffer and the order becomes 110 cubic feet, or 4.07 cubic yards. In bags, that is 110 ÷ 0.6 = 183.3, so 184 bags of 80-lb mix (245 bags of 60-lb, 294 bags of 50-lb). In trucks, 4.07 ÷ 10 = 1 truckload. At $150 per cubic yard, ready-mix costs 4.07 × $150 = $611.11; in bags at $5.50 each it costs 184 × $5.50 = $1,012.00 — so the truck saves $400.89 on this job. A smaller job flips the other way: a 10 × 10 ft slab at 4 inches needs 1.23 cubic yards net, or 1.36 yards with the buffer, which is 62 bags of 80-lb mix. That is a one-person bag job, and a truck would cost more once delivery and short-load fees are added.

Bags or Ready-Mix: Which Is Cheaper?

Bags win on small jobs and trucks win on big ones, and the crossover sits near 1 cubic yard. One cubic yard takes 45 bags of 80 lb, 60 bags of 60 lb or 72 bags of 50 lb. Below about 1 cubic yard, bags are usually cheaper: there is no delivery fee, no minimum load and you mix only what you need, one bag at a time. Above about 1 cubic yard the truck is almost always cheaper, and the gap grows fast — the patio above saves $400.89 by truck. But watch the fees. Most ready-mix companies will deliver as little as 1 cubic yard, yet orders below 4 or 5 yards typically incur a short-load fee of $100 to $250, and some plants charge extra for Saturday pours or for waiting time if your crew is not ready. Standard transit mixer trucks hold 8 to 11 cubic yards, so a 13.25-cubic-yard RV pad needs 2 trucks, and the second truck must arrive while the first load is still workable. Get the price per cubic yard, the delivery fee, the short-load fee and the waiting-time rate in writing before you book.

How Thick Should the Concrete Be?

Thickness is not a guess — it follows the load. Patios, walkways and shed pads are 4 inches. Driveways for cars are 4 inches, but 5 to 6 inches for heavy vehicles, RVs and delivery trucks. A 6-inch slab uses 50% more concrete than a 4-inch slab of the same area, so getting this right matters to the order: a 20 × 20 ft driveway at 4 inches needs 4.94 cubic yards net, while the same driveway at 6 inches needs 7.41 cubic yards. Footings and structural slabs follow the building code and the engineer’s drawings, not a rule of thumb — footing depth must pass below the local frost line, and reinforcement (rebar grid or wire mesh, usually spaced 12 to 18 inches on centre) belongs in the plan, not as an afterthought. For a monolithic slab foundation, the floor and the thickened edge footing are poured in one go; a 40 × 30 ft garage on that system needs 24.85 cubic yards.

Ordering Day: What to Get Right

Order the concrete last, after the forms are set, the base is compacted and the reinforcement is in place. Confirm the mix (strength, usually 3,000–4,000 psi for residential flatwork), the slump (how wet it is — wetter is easier to place but weaker when it cures), and the arrival time. According to ASTM C94, ready-mix must be fully discharged within 90 minutes of batching or before the drum reaches 300 revolutions, so the crew, the wheelbarrows and the screed boards must be ready before the truck arrives. Have a backup plan for leftover concrete — fence post holes, stepping stone moulds or a trash can pad — because a truck cannot take it back. And keep the slab damp for the first days: concrete gains strength by curing, not by drying out, and it reaches full design strength in about 28 days.

Common Mistakes That Cost Money

The most expensive mistake is mixing units: entering thickness in inches while length and width are in feet, without dividing by 12, overstates the volume by twelve times. The second is ordering the exact net volume with no waste buffer — uneven subgrade, spillage and form movement always use more than the drawings say, and running short mid-pour leaves a cold joint, a weak line where the old concrete had already started to set before the new concrete arrived. The third is forgetting the subgrade: concrete poured on soft, uncompacted ground cracks, however good the mix is. Compact the base, set the forms level, and order 10% extra — 15% when pouring against rough excavation with no forms. Measure twice, order once, and pour with the crew ready.

Try the calculator

Work out your own numbers with the Concrete Calculator Yards.

Open Concrete Calculator Yards
Authoritative Sources & Data References:
  • National Ready Mixed Concrete Association (NRMCA) — Ordering Ready Mixed Concrete
  • American Concrete Institute (ACI 318 — Building Code Requirements)
  • ASTM C94 / C94M — Standard Specification for Ready-Mixed Concrete

Published 2026-11-18. Figures in this guide were checked against the matching calculator on this site. Numbers that change with the law or with prices — tax rules, statutes and supplier rates — should be confirmed against the source before you rely on them.